Cost and schedule overruns in large hydropower dams: an assessment of projects completed since 2000

  • Judith Plummer Braeckman
  • , Tim Disselhoff
  • , Julian Kirchherr

    Research output: Journal contributions › Journal articles › Research › peer-review

    21 Citations (Scopus)

    Abstract

    This paper presents novel data on cost and schedule overruns in recent dam projects started and completed since 2000 and compares them with pre-existing data sets on projects started before 2000. Combining these data, a meta-data set was created of 184 cost overrun and 191 time overrun data points. For post-2000 projects, the average cost overrun was 33% and schedule overrun was 18% as compared with 46% and 37% respectively for pre-2000 projects. While a decrease in the averages was observed, the change in cost overruns is not statistically significant, whereas the change in time overruns is significant.
    Original languageEnglish
    JournalInternational Journal of Water Resources Development
    Volume36
    Issue number5
    Pages (from-to)839-854
    Number of pages16
    ISSN0790-0627
    DOIs
    Publication statusPublished - 02.09.2020

    Bibliographical note

    Publisher Copyright:
    © 2019 Informa UK Limited, trading as Taylor & Francis Group.

    Research areas and keywords

    • Environmental planning
    • Sustainability sciences, Management & Economics
    • Large dams
    • hydropower
    • forecasting
    • cost and schedule estimatesw
    • World Commision on Dams

    ASJC Scopus Subject Areas

    • Development
    • Water Science and Technology

    Fingerprint

    Dive into the research topics of 'Cost and schedule overruns in large hydropower dams: an assessment of projects completed since 2000'. Together they form a unique fingerprint.

    Cite this